一、通風(fēng)管道在安裝時(shí)的注意事項(xiàng):
I. Notices for Ventilation Pipeline Installation:
(1)當(dāng)風(fēng)管與風(fēng)機(jī)連接時(shí),應(yīng)在進(jìn)出風(fēng)口處加軟接頭,其軟接頭的斷面尺寸應(yīng)與風(fēng)機(jī)進(jìn)出風(fēng)口一致。軟管接頭一般可采用帆布、人造革等材料,軟管長(zhǎng)度不宜小于200,松緊度應(yīng)適宜,柔性軟管可緩沖風(fēng)機(jī)的振動(dòng)。
(1) When the duct is connected with the fan, the soft joint should be added at the inlet and outlet of the fan. The cross-section size of the soft joint should be the same as that of the inlet and outlet of the fan. The hose joint can generally be made of canvas, artificial leather and other materials. The length of hose should not be less than 200, the tightness should be appropriate, and the flexible hose can cushion the vibration of the fan.
(2)當(dāng)風(fēng)道與除塵設(shè)備、加熱設(shè)備等連接前,應(yīng)待設(shè)備安裝完畢后,按實(shí)際測(cè)繪的圖紙進(jìn)行預(yù)制和安裝。
(2) When the air duct is connected with dust removal equipment and heating equipment, it should be prefabricated and installed according to the actual surveying drawings after the installation of the equipment.
(3)風(fēng)道安裝時(shí),進(jìn)、出風(fēng)日宜在風(fēng)道預(yù)制時(shí)開出洞口,如需在安裝完畢的風(fēng)道上現(xiàn)開風(fēng)口,其接口處應(yīng)嚴(yán)密。
(3) When the duct is installed, the inlet and outlet days should be opened when the duct is prefabricated. If the outlet is to be found in the installed duct, the interface should be tight.
(4)當(dāng)輸送含凝結(jié)水或含濕量較大的氣體時(shí),其水平管道宜設(shè)有坡度,并在低點(diǎn)處接排水管。安裝時(shí)風(fēng)道底部不宜出現(xiàn)縱向接縫,對(duì)底部有接縫處應(yīng)進(jìn)行密封處理。
(4) When conveying gas with condensate water or high moisture content, the horizontal pipeline should have a slope and be connected with a drainage pipe at a low point. Longitudinal seams should not appear at the bottom of the duct during installation. Sealing treatment should be carried out at the seams at the bottom.
(5)對(duì)輸送易燃、易爆氣體的鋼板風(fēng)道,在風(fēng)道連接法蘭處應(yīng)安裝跨接線,并與靜電接地網(wǎng)連接。
(5) For steel plate air ducts conveying flammable and explosive gases, a cross connection shall be installed at the flange of the air duct connection and connected with the electrostatic grounding grid.
二、通風(fēng)管道安裝程序:
2. Installation procedures for ventilation pipes:
(1)風(fēng)管組裝:當(dāng)風(fēng)管較短時(shí),可一次在地面組裝而成,當(dāng)風(fēng)管較長(zhǎng)時(shí),可視安裝場(chǎng)地的情況,在地面分段組裝。組裝時(shí)應(yīng)盡量調(diào)整風(fēng)道的中心度和水平度,避免風(fēng)管扭曲或上下起波,左右擺龍,每段風(fēng)道不宜超過10m.組裝時(shí),墊片應(yīng)墊平,法蘭螺栓應(yīng)均勻擰緊,螺母帽均朝向同一方向。
(1) Air duct assembly: When the air duct is short, it can be assembled on the ground at one time. When the air duct is long, it can be assembled on the ground in segments according to the situation of the installation site. When assembling, adjust the centrality and levelness of the duct as far as possible to avoid the distortion or upside and downs of the duct, swing dragons from left to right, and each duct should not exceed 10 m. When assembling, gaskets should be padded flat, flange bolts should be tightened evenly, and nuts should be in the same direction.
(2)風(fēng)管就位:風(fēng)管就位前應(yīng)檢查全部支架的水乎度和標(biāo)高、檢查支架的牢固程度,風(fēng)管就位可采用直接和吊具兩種方法。對(duì)風(fēng)管斷面較小,又位置較低的可采用人工就位方法,只需搭設(shè)簡(jiǎn)易腳手架即可。當(dāng)風(fēng)管斷面較大且管段較長(zhǎng)時(shí),可采用滑輪、倒鏈、大繩等方法吊裝。世紀(jì)星介紹為了便于風(fēng)道就位,一般多采用將風(fēng)道吊在腳手架上,然后再將其抬放在風(fēng)道支架上的方法。腳手架應(yīng)沿其風(fēng)道長(zhǎng)度方向搭設(shè),高度和位置應(yīng)適合施工操作,吊裝順序應(yīng)先干管后支、立管,吊起時(shí),吊點(diǎn)應(yīng)牢固,兩吊點(diǎn)應(yīng)均勻受力。垂直風(fēng)管可采用人工和大繩輔助就位。調(diào)整風(fēng)管保證垂直度要求。
(2) Air duct positioning: Before air duct positioning, the water alignment and elevation of all brackets should be checked, and the firmness of brackets should be checked. Direct and suspension methods can be used for air duct positioning. For the smaller section and lower position of the air duct, the manual positioning method can be adopted, and only simple scaffolding can be set up. When the section of air duct is large and the section is long, pulleys, chains and ropes can be used for hoisting. Century Star introduced that in order to facilitate the placement of the air duct, the method of hanging the air duct on the scaffolding and then lifting it on the air duct bracket is usually adopted. The scaffolding should be erected along the length direction of its air duct, and the height and position should be suitable for construction operation. The lifting sequence should first be trunk pipe, then branch pipe and riser pipe. When lifting, the lifting point should be firm and the two lifting points should be uniformly loaded. Vertical ducts can be positioned with manual and large rope assistance. Adjust the air duct to ensure the verticality requirement.
(3)風(fēng)道調(diào)直:就位在支架上的風(fēng)道,應(yīng)撥正位置,調(diào)整風(fēng)道橫平豎直,然后再按圖集要求固定。
(3) Straightening the air duct: The air duct positioned on the support should be positioned to adjust the horizontal and vertical air duct, and then fixed according to the requirements of the atlas.
以上就是山東通風(fēng)管道對(duì)于通風(fēng)管道注意事項(xiàng)的介紹,更多行業(yè)信息請(qǐng)聯(lián)系我們http://m.hwzxw.net。
The above is the introduction of Shandong ventilation pipeline to the matters needing attention. For more information, please contact us at http://m.hwzxw.net.
上一篇:黑白鐵加工的管道特點(diǎn)及應(yīng)用
下一篇:通風(fēng)管道的安裝方法與安裝方式
相關(guān)